KEY STAGE ACTIVITY | NORMAL TIME | IMMEDIATE PREDECES SOR | Human Resource | ||
ACTIVITY | DESCRIPTION | (DAYS) | 1 | 2 | |
A | Locate Bldg | 25 | – | 4 | |
B | Plan layout | 10 | – | 2 | |
C | Clean up bldg | 19 | B | 3 | |
F | Quotes for mods | 25 | A | B | 2 |
G | Furniture quote | 20 | B | 2 | |
H | Recruit staff | 25 | D | G | 3 |
D | Get all approvals | 25 | C | 2 | |
M | Install mods | 25 | F | D | 5 |
L | Design fittings | 20 | D | 5 | |
K | Design IT&C"e | 20 | D | 5 | |
P | Install IT&C | 10 | K | 4 | |
N | Install fitting | 10 | L | M | 4 |
R | Install office equipt | 5 | P | N | 4 |
S | Install furniture | 5 | N | 4 | |
T | Test IT&C equip | 10 | R | 3 | |
U | Move staff | 5 | S | H | 3 |
V | Final testing | 4 | U | T | 4 |
W | Grand opening | 1 | V | E | 6 |
E | Plan opening | 5 | A | 3 |
Question:
- how long the project will take? (tutorial:https://www.youtube.com/watch?v=mAZ5e5sNiJc
- create gantt chart of this project (tutorial here:http://devipratami.staff.telkomuniversity.ac.id/kuliah-membuat-gantt-chart-proyek-dan-lintasan-kritis/
- how many workers recruited in this project?
- identify the critical path! (tutorial: https://www.youtube.com/watch?v=A83LRaXJuXk
- if activity P is slipped until 10 days, investigate the project completion!